Backup plan does not work correctly with full backup
Hi,
I created new backup plans last month and full backup seems to not work.
details of plan:
Full -> 1st day of each month at 01:00
Incremental -> Mon-Tue-Thu-Sat at 04:00
Since the first full backup the 09 July 2015 I only have incremental backup.
Is there a bug? or something not well configured?
Others plans which have as trigger the first "monday" (for example) of each month works well.
Any idea?
Regards,
Clément
(same version for management console & agents -> 11.5.39029)

- Log in to post comments

Thanks to your advice, I checked log files and I think I know why the full backup did not started.
The vault was full during the weekend and many backups jobs was stopped and needed interaction.
To my mind, I reloaded job for incremental and ignore full backup. Or maybe incremental job which happens 2 hours after full job overwrite it and I only had an alert in order to launch again incremental. (Maybe you have the answer)
For your information, the checkbox was already checked in the backup plan.
I will convert the first incremental backup of August as a full and it will be OK.
Thanks for your help.