hello, i'm newby to acronis... i would like to build a schedule to take a full (complete) backup twice a month on the 1 and on the 15 and keep the latest version of those... so i will always have a version of the 1 and a version of the 15... could you please give me a step by step guide... many thanks for helping
- Log in to post comments
If you set up a task that does full backups, keeps only the last 4 versions, choose the monthly options in the scheduler, and select the 1 and 15 of each month.
The first month, you will get one backup on the 1 and another on the 15,
The second month, you will get a second "first of the month" backup, and same for the day 15,
The third month, ATI will first create a third "first of the month" backup, then ATI will delete the first backup you made, and so on so forth.
So you will need space for 5 full backups.