Duplicate Tasks
Running AB&R 10 build 11639.
I noticed that one of my backup jobs is running twice, one right after the other. In looking in the tasks for that server all the tasks are duplicated. ie two full backups, two incrementals and two differential, plus duplicated clean up tasks . In the screen where I select one of the duplicated tasks I am unable to delete it.
Anyway I can remove the duplicate tasks short of deleting the machine and policy and readdind?
Thanks

- Se connecter pour poster des commentaires

Yana,
Thanks for the reply and sorry it took so long to get back.
I have downloaded the schedule manager and the updated schedular. Before I run thes programs I need to verify somthing. When I open the command window to run the schedmgr.exe will I be able to specify or choose which task to 'zap'? There are only a couple hundred tasks there and I would hate to loose all of them.
Larry
- Se connecter pour poster des commentaires

Dear Larry!
Thank you for your reply and your question, I appreciate it!
task zap command will delete all the tasks. In case you need to remove just one task, please follow the below instructions:
- Run schedmgr.exe and issue this command
get list
It will provide you with the list of tasks you have - Find the one you need to delete and enter the following command:
task [task_number]
This will get you to this task menu - As soon as you are in the task menu, enter
Delete
and the task will be removed
It is preferable to remove all the tasks during the updated, but in your case I understand how inconvenient it will be. So please remove just the duplicated plans and proceed with the update.
Let me know in case something's confusing you - I will be happy to assist!
Thank you
- Se connecter pour poster des commentaires