If I have a full and a couple incremental backs and want to add another incremental, when it says "add to existing archive" do I select the "Full" backup file or the last "Incremental" file? Thanks

0 Users found this helpful

If the task is already made, just running the task should automatically add the incremental to the archive.

If for some reason you've started a new task and want that to carry on the archive, then select the last incremental.

You probably could also select the full, but the incrementals might just go out of sync.