Hi, 

We are running Acronis Backup Advanced 12.5 SP1 and configured three storage nodes on three sites.

These storage nodes store their data on a NAS devices via SMB and the sites are connected to each other through a 20 or 10MB dedicated EVPN.

I created three Replication plans to replicate the backups from the storage nodes from site A to B and B to A and C to A.

When I start the Replication plan it always displays "0% completed" .. when I check on the storage device I can see that the data is adding up. And after I while the data is replicated and the plan completes the progress indication goes from 0% to 100% at once .. so we do not have any indication of when the job will be finished .. and also Acronis states that there is no pogress and we keep getting messages "Activity is not responding" ..very annoying!!

How can I fix this?!

0 Users found this helpful

know issue

storage nodes do not report progress back to management server

the developers are working on it ... allegedly