timeout on scheduled task.
Thread needs solution
Hello,
We are currently deploying B&R on laptops. We scheduled task to perform backups during week days. Backup files are writen on a NAS, which is located in the office.
Everything works fine if the laptop is in the office (and powered on) when scheduled task is launched.
I've the following problem:
Some users use to leave the office during several days, so the laptop will not be linked with the NAS during a long time.
When they come back to the office, B&R launch all the pending tasks, slowering down the computer for a long time
Is there a way to configure B&R to prevent this problem ?
I've never seen a option to define a timeout for a task ...
Thanks !
Mer, 09/22/2010 - 09:23