Run Two Different Backups at Same Time?

Thread needs solution

Source: C (Operating System)
Destination: F
Destination: G

Can Acronis True Image 2012 run TWO scheduled backups at the SAME time with the SAME source drive?

The first is a nonstop backup of C drive (operating system) to F drive
The second is a weekly disk image of C drive (operating system) to G drive

Both are imaging the same C drive at the same time. Is this possible?

Thanks

FYI: I know nonstop consolidates backups and has weekly included. I just want to know if Acronis can run both a nonstop and disk backup at the same time of the same source drive.

0 Users found this helpful

NSB and a task can be run at the same time.

You can also start several tasks on the same or diff source drives and each will run in turn after the other is complete -- ati will queue them up for you. IF you have tasks scheduled to run at the same time, in that case ati will also queue them up and run them one after the other.